Weekly roadworks update – March 4

The multimillion-pound Stoneferry improvement scheme continues over the next week with overnight resurfacing work in Stoneferry Road and Chamberlain Road.

Until Wednesday March 9, Stoneferry Road will be closed on weeknights (7pm to 6am) southbound between Bandstand Roundabout and Ferry Lane roundabout.

On Thursday March 10 and Friday March 11, Chamberlain Road will be closed overnight (7pm to 6am) from the Stoneferry Road roundabout to the entrance of Base Business Space.

Councillor Dean Kirk, Hull City Council’s portfolio holder for transportation, roads and highways, said: “The Stoneferry Corridor project is currently on course for completion in late spring, after which motorists, businesses and residents in the area will be able to enjoy the full benefits of a much-improved road network.”

Read the full story

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change, so motorists are also advised to check one.network for the latest updates.

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – St James Street to Market Place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
A63 improvement scheme – Brighton Street to Roger Millward Way 07 March 2022 25 March 2022 Road closure eastbound from Brighton Street to Roger Millward Way and westbound from Roger Millward Way to Daltry Street. Weeknights from 8pm – 6am. 40 Seven Ltd
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2022 Enable H&S and safe systems of works for operatives working on the scheme. National Highways
Bellfield Avenue 10 January 2022 11 April 2022 Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times. HCC – MP&I
Bellfield Avenue 28 March 2022 30 March 2022 Road closure for carriageway resurfacing. Works to take place between 7pm – 6am. Local diversion in place. Section 278
Beverley Road 07 March 2022 22 April 2022 Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane Closure Northern Gas Networks
Beverley Road – Brunswick Arcade 04 October 2021 01 September 2022 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. HCC – MP&I
Bowlalley Lane 14 February 2022 05 March 2022 Road closure to reinstate carriageway gas trenching and install raised table. Local diversion in place to allow access for residents / businesses. HCC – MP&I
Chanterlands Avenue 28 February 2022 11 March 2022 Lane Closure. Excavation in footway and carriageway adjacent to 10 Chanterlands Avenue (nr cemetery gates) Yorkshire Water
Hall Road 15 March 2022 25 March 2022 Cherry picker to access telecoms mast for testing and maintenance works from 9.30am-3.30pm approx 100m west of Thorpepark Road. Two-way signals. O2 (GS Hall)
Hall Road 08 February 2022 11 March 2022 Gas pipe replacement scheme. Located outside of The Parks Children’s Centre. Temporary traffic signals required due to location of gas pipe. Northern Gas Network
Hessle Road (12-month Scheme) 23 August 2021 04 September 2022 Footway reconstruction. HCC – MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8) 04 January 2022 11 September 2022 Full footway reconstruction scheme. MP&I – Highways Strategy & Design
Hopewell Road 14 March 2022 24 April 2022 Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. HCC – MP&I
Humber Street 07 February 2022 19 March 2022 Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway. HCC – MP&I
Inglemire Lane 17 March 2022 17 March 2022 Telecoms mast testing and maintenance works from 9.30am-3.30pm approx 100m west of Thorpepark Road. Two-way signals. O2 (GS Hall)
Lowgate Footway Scheme – West / East Footway 22 October 2021 16 April 2022 Footway repair scheme. Scheme delayed due to signal failure on A63. Northbound closure. Current traffic management set-up to remain in place for duration of scheme. HCC – MP&I
Lowgate Footway Scheme – Bishop Lane / Chapel Lane 14 March 2022 17 March 2022 Road closure for duct crossing across junctions of Bishop Lane and Chapel Lane. Works to take place between 6pm and 11pm. HCC – MP&I
Saltshouse Road 21 February 2022 05 March 2022 Carriageway repair works at junction with Battersea Close. Multi-way signals from 9.30am-3.30pm. Streetscene Highway Operations
Stoneferry Rd Scheme – Woodhall Street to Lorraine Street 01 April 2021 01 April 2022 Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 01 April 2022 Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I / Colas
Stoneferry Rd Scheme – Bandstand Roundabout to Ferry Lane Roundabout 03 March 2022 10 March 2022 Mainline surfacing to Stoneferry Road between Bandstand Roundabout and Ferry Lane Roundabout. Closures from 7pm to 6am, Mon to Fri nights. HCC – MP&I / Colas
Stoneferry Rd Scheme – Chamberlain Road 10 March 2022 12 March 2022 Surfacing to Chamberlain Road. Road closure between 7pm and 6am. Chamberlain Road from junction with Stoneferry Road to the entrance to Base Business Space. HCC – MP&I / Colas
Stoneferry Rd Scheme – West Carr Lane 14 March 2022 17 March 2022 Surfacing to West Carr Lane. Road closure from NR Burnett entrance to junction with Stoneferry Road / Holwell Road Closures from 7pm to 6am, Mon to Fri nights. HCC – MP&I / Colas
Stoneferry Rd Scheme – Sutton Road 17 March 2022 22 March 2022 Surfacing of Sutton Road, Road closure eastbound from junction with Holwell Roundabout for approx 120m. HCC – MP&I / Colas
Stoneferry Rd Scheme – Holwell Road 17 March 2022 22 March 2022 Surfacing of Holwell Road. Road closure northbound from junction with Sutton Road. HCC – MP&I / Colas
Wincolmlee 04 February 2022 10 March 2022 Road closure for emergency gas work. Northern Gas Network
Wincolmlee (Phase 2) 31 January 2022 04 March 2022 Road closure for new connection and cable upgrades. Northern Powergrid