Dorset Road Fix 2022 – resurfacing June 2022

Dorset Highways maintenance gangs are out across the council area continuing to repair road damage.

workers on a paving machine

As we move into the summer months, where main routes are busier, our work will move away from strategic routes and into more residential areas.

To allow this work to take place safely, the area of the road being worked on will be closed. Daytime road closures are 9am to 4pm and night work is usually from 7pm to 6am.

We will do our best to keep you updated if our schedule of work changes.

June sites

Wimborne Road, Tarrant Keyneston – 6 June to 11 June
road closed 9am to 4pm

B3069 Kingston Hill – 13 & 14 June
road closed 8pm to 6am

Station Road, Sturminster Newton – 15 June to 17 June
road closed 8pm to 6am

Parmiter Drive, Wimborne – 20 June to 23 June
road closed 9am to 4pm

Moorlands Road & Moorlands Rise, West Moors – 23, 24 & 27 June
road closed 9am to 4pm

Hazel Drive, Ferndown – 24, 27 & 28 June
road closed 9am to 4pm

Parley Close, West Parley – 27 to 29 June
road closed 9am to 4pm

Linden Road & Linden Close, West Parley – 28 to 30 June
road closed 9am to 4pm

Pilford Heath Road, Colehill – 29 June to 1 July
road closed 9am to 4pm

Legg Lane, Wimborne – 30 June, plus 1 & 4 July
road closed 9am to 4pm

Road maintenance

Using a variety of surface treatments ensures that more of Dorset Council’s roads get repaired with the budget available, compared to using resurfacing alone.

Please use our online form to report highway-related issues/damage. This goes directly to the local community highways officer for assessment.