Weekly roadworks update – June 6

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

Location Start date Due date Summary of works Utility/HCC name
A63 improvement scheme – St James Street to Market Place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2024 Enable H&S and safe systems of works for operatives working on the scheme. National Highways
Beverley Road – Brunswick Arcade 04 October 2021 01 April 2023 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. HCC – MP&I
Beverley Road 06 June 2022 10 June 2022 Construction of additional length of off-road cycle track. Lane closure 9.30am – 3.30pm. Mizzen Road to city boundary. HCC – MP&I
Calvert Lane 16 May 2022 10 July 2022 Carriageway resurfacing scheme from approximately 50m north of Boundary Way to Calvert Lane fire station. Road closed. Diversion in place. Access to be maintained at all times. HCC – MP&I
Charles Street 04 April 2022 15 June 2022 Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. HCC – MP&I
Cleveland Street 13 June 2022 08 July 2022 Movement of traffic island. Near junction of Bedford Street. Lane closure. Two-way signals to be in place for one night only. HCC – MP&I
Gillshill Road 24 May 2022 07 June 2022 Works between Sutton House Road and Ings Road junction to establish new gas connection. Two-way signals. Northern Gas Network
Great Union Street 23 May 2022 26 June 2022 Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. HCC – MP&I
Greenwood Avenue 06 June 2022 08 June 2022 Installation of telecommunications cabinet. Lane closure with multi-way signals from 9.30am – 3.30pm. HCC – MP&I
Hawthorne Avenue 20 June 2022 24 June 2022 Level crossing and track survey. Lane closure with two-way signals from 11pm – 5.30am. Network Rail
Hessle Road (12-month Scheme) 23 August 2021 04 September 2022 Footway reconstruction. HCC – MP&I
High Street 16 May 2022 18 July 2022 Laying ducting, kerbs/ edgings, installation of cobbled paving under Myton Bridge. Multi-way signals. National Highways
Holderness Road (Victor St to Southcoates) (PHASES 1-8) 04 January 2022 11 September 2022 Full footway reconstruction scheme. MP&I – Highways Strategy & Design
Lowgate 13 June 2022 14 June 2022 Guildhall clock tower maintenance. Road closure outside Guildhall from 8am on Monday 13 until 6pm on Tuesday 14. Local diversion in place. Swift Traffic Management
Park Street 06 June 2022 17 June 2022 Replacement of gas main. Westbound road closure (Caughey Street to Spring Bank). No access from Spring Bank. Access from Park Street to Spring Bank still available. Northern Gas Network
Priory Way 01 April 2022 31 March 2023 Major improvement scheme. HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Lorraine Street 01 April 2021 01 July 2022 Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 01 July 2022 Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. HCC – MP&I / Colas
Stoneferry Rd Scheme – Bandstand Roundabout 10 June 2022 11 June 2022 Installation of loop detectors for new traffic signals. Overnight road closure (7pm to 6am) on south side of Bandstand Roundabout between Stoneferry Road legs. HCC – Colas
Stoneferry Rd Scheme – Bandstand Roundabout 11 June 2022 12 June 2022 Installation of loop detectors for new traffic signals. Overnight road closure (7pm to 6am) on northern side of Bandstand Roundabout between Holwell Road exit and entry. HCC – Colas
Stoneferry Rd Scheme – Bandstand Roundabout 12 June 2022 13 June 2022 Installation of loop detectors for new traffic signals. Overnight road closure (7pm to 6am) on west side of Bandstand Roundabout between West Carr Lane exit and entry. HCC – Colas
Stoneferry Rd Scheme – Leads Road 25 April 2022 29 July 2022 Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. HCC – MP&I COLAS
Stoneferry Rd Scheme – Leads Road 29 July 2022 01 August 2022 Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. HCC – MP&I COLAS
Stoneferry Rd Scheme – Sutton Road 03 May 2022 01 July 2022 Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. HCC – MP&I
Stoneferry Rd Scheme – West Carr Lane 10 June 2022 11 June 2022 Installation of Loop detectors for the new traffic signals and High Friction surfacing and road markings. Overnight road closure (7pm to 6am) from Bandstand Roundabout to entrance of NR Burnett. HCC – Colas