Weekly roadworks update – February 11

This week, it was announced that overnight works would be taking place at the junction of Sutton Road and Leads Road from Monday 14 February.

The carriageway duct works are part of the Stoneferry improvement scheme and are expected to last about two weeks.

Councillor Dean Kirk, Hull City Council’s portfolio holder for transportation, roads and highways said: “The Stoneferry Corridor project is currently on course for completion in late spring, after which time motorists, businesses and residents in the Stoneferry area will be able to enjoy the full benefits of a much-improved road network.”

Full story here

Below is a breakdown of roadworks taking place across Hull over the next few weeks.

All dates are subject to change, so motorists are also advised to check one.network for the latest updates, as well as detailed maps and diversion routes.

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2022 Enable H&S and safe systems of works for operatives working on the scheme. National Highways
A63 improvement scheme – St James Street to Market Place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
Bellfield Avenue 10 January 2022 11 April 2022 Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times. HCC – MP&I
Bellfield Avenue 28 March 2022 30 March 2022 Road closure for carriageway resurfacing. Works to take place between 7pm – 6am. Local diversion in place. Section 278
Beverley Road – Brunswick Arcade 04 October 2021 01 September 2022 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. HCC – MP&I
Beverley Road – Mizzen Road to Windle Avenue 05 January 2022 11 February 2022 Construction of new cycle track and footpath on the existing footpath and verge. Lane closure. MP&I ARBPMLTD
Bowlalley Lane 14 February 2022 28 February 2022 Road closure to reinstate carriageway gas trenching and install raised table. Local diversion in place to allow access for residents / businesses. HCC – MP&I
Hall Road 16 February 2022 17 February 2022 Two-way signals for telecoms maintenance using cherry picker near junction with Thorpe Park Road. Footway closure. Pedestrian walkway provided. Activities to take place between 9.30am and 3.30pm. All other times highway to be clear. T-Mobile Ltd – SIAE
Hessle Road (12-month Scheme) 23 August 2021 04 September 2022 Footway reconstruction. HCC – MP&I
Hessle Road 07 February 2022 14 February 2022 Installation of sewer pipe. Inbound closure only near junction of Priory Way. Local diversion in place. Section 278 Development
Holderness Road (Victor St to Southcoates) (PHASES 1-8) 04 January 2022 11 September 2022 Full footway reconstruction scheme. MP&I – Highways Strategy & Design
Holderness Road 24 January 2022 11 February 2022 Excavation for new cable connection. Northern Powergrid
Holwell Road 15 February 2022 17 February 2022 Land and erect new streetworks pole on the grass verge on Holwell Road 20m from junction with Goodhart Road. Multi-way signals. Two-way pedestrian light with marshals to be used when lifting is in progress. Working hours will be 8am-6pm. Vodafone
Hopewell Road 14 March 2022 24 April 2022 Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. HCC – MP&I
Humber Street 07 February 2022 19 March 2022 Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway. HCC – MP&I
Lowgate Footway Scheme – West / East Footway 22 October 2021 16 April 2022 Footway repair scheme. Scheme delayed due to signal failure on A63. Current traffic management set-up (northbound closure) to remain in place for duration of scheme. HCC – MP&I
Marfleet Lane 21 February 2022 23 February 2022 Carriageway repair works (sunken trench). Multi-way signals. On top of the railway bridge. Works to take place for one day only from 9.30am-3.30pm. HCC – Highway Operations
Preston Road 07 February 2022 16 February 2022 Bus stop relocation. Narrowing of central reserve to give 3m-width traffic lane; slip trench on the central reserve. Lane closure to start at 9.30am on first day of works. HCC – Bridges
Saltshouse Road 21 February 2022 23 February 2022 Carriageway repair works at junction with Battersea Close. Multi-way signals from 9.30am-3.30pm. Streetscene Highway Operations
Saltshouse Road 21 February 2022 23 February 2022 Carriageway repair works at junction with St Bartholomew’s Way. Multi-way signals from 9.30am-3.30pm. Streetscene Highway Operations
Silver Street 04 January 2022 13 February 2022 Road closure due to installation of automated bollards. HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Lorraine Street 01 April 2021 01 April 2022 Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout 23 April 2021 01 April 2022 Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I / Colas
Sutton Road 14 February 2022 24 February 2022 Installation of duct crossings for new traffic signals at junction of Leads Road /Sutton Road. Multi-way signals. works to take place between 7.30pm-6am. Carriageway will be clear at all other times. HCC – MP&I COLAS
Sutton Road 18 February 2022 19 February 2022 Minor, non-excavation works near junction with Stockholm Road from 7pm to 5am. Illuminated stop/go boards. O2 (GS Hall)
Thomas Clarkson Way 16 February 2022 17 February 2022 Thomas Clarkson Way southbound. Two-way lights in operation to allow safely removal of variable-messaging sign. Activities to take place 9.30am-3.30pm all other times highway to be clear. StreetScene – Traffic Signals
Wincolmlee (Phase 2) 31 January 2022 04 March 2022 Road closure for new connection and cable upgrades. Northern Powergrid
Wold Road 28 February 2022 04 March 2022 Installation of new telecoms pole at junction with Willerby Road and Seagrave Grove. Work from 9.30am to 3.30pm. Multi-way signals in place for short durations. Carriageway to be clear at all other times. T-Mobile