Weekly roadworks update – April 22

Major regeneration works at Brunswick Arcade are ahead of schedule.

The protective hoardings and traffic cones on the short stretch of Beverley Road between Norfolk Street and Trafalgar Street have been moved back towards the kerb, allowing the road two return to two lanes southbound. There remains only one lane northbound at this stage.

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

Location Start date Due date Summary of works Utility/HCC name
A63 improvement scheme – St James Street to Market Place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2022 Enable H&S and safe systems of works for operatives working on the scheme. National Highways
Beverley Road 07 March 2022 27 April 2022 Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane Closure Northern Gas Networks
Beverley Road – Brunswick Arcade 04 October 2021 01 September 2022 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. HCC – MP&I
Bishop Lane 16 May 2022 19 May 2022 Install new water supply connection. Full road closure. Local diversion in place. Yorkshire Water
Carr Lane (About Us event) 30 April 2022 06 May 2022 Carr Lane closed from junction with Chariot Street to junction with Queens Dock Avenue, 8pm-11.30pm daily. Diversion in place. About Us event
Charles Street 04 April 2022 29 April 2022 Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. HCC – MP&I
Great Union Street 23 May 2022 26 June 2022 Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. HCC – MP&I
Hall Road 26 April 2022 26 April 2022 Telecoms pole maintenance. Two-way signals in place from 9.30am-3.30pm. O2 (GS Hall)
Hessle Road (12-month Scheme) 23 August 2021 04 September 2022 Footway reconstruction. HCC – MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8) 04 January 2022 11 September 2022 Full footway reconstruction scheme. MP&I – Highways Strategy & Design
Hopewell Road 14 March 2022 29 April 2022 Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. HCC – MP&I
Howdale Road – Phase 2 26 April 2022 04 May 2022 Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured. Streetscene Highway Operations
Ings Road 09 May 2022 19 May 2022 Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance. Northern Gas Network
Stoneferry Rd Scheme – Woodhall Street to Lorraine Street 01 April 2021 01 August 2022 Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 01 August 2022 Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I / Colas
Stoneferry Rd Scheme – Sutton Road 20 April 2022 22 April 2022 Removal of existing splitter islands in the junction of Sutton Road and Leads Road. night. Multi-way signals. Works will take place 7pm to 6am. HCC – MP&I COLAS
Stoneferry Rd Scheme – Leads Road 25 April 2022 29 July 2022 Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. HCC – MP&I COLAS
Stoneferry Rd Scheme – Leads Road 29 July 2022 01 August 2022 Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. HCC – MP&I COLAS
Stoneferry Rd Scheme – Sutton Road 03 May 2022 01 July 2022 Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. HCC – MP&I
Wincolmlee 15 April 2022 28 April 2022 Emergency works. Low-voltage mains cable fault. Two-way signals between junction of George Street and Scott Street. Northern Power Grid
Wincolmlee 18 April 2022 29 April 2022 Works originally postponed due to gas leak. Power main replacement scheme. Multiway signals, junction of Wincomlee/ Air Street / Bank Side. Northern Power Grid